__color__,ticket,summary,component,priority,status,milestone,type,owner,severity,created,_changetime,_description,_reporter 2,1,Inventory of Sensors,sensor,critical,closed,Buoy-System-2010,task,haines,desired,1277815567,1285875803,Create an inventory (database or spreadsheet) of sensors to with * make_ model_ serial number_ * current location_ * last calibration date_ calibration period_ * status (normal_ broken_ out-of-cal_ missing). We need to be able to track which sensors need fixing and/or calibration. ,haines 2,2,Prepare buoys for shipment to YSI,system integration,critical,closed,Buoy-System-2010,task,haines,must have,1277817706,1285875484,Collect all components for YSI build out of the buoy systems * ~~one working set of sensors (to start work)~~ * ~~ensure buoy batteries function~~ * ~~collect all correct cables and connectors to sensors~~ * ~~collect components to sensors (e.g. rm young wind serial interface unit)~~ * ~~remove any IMS equipment that Tony and Rick do not want deployed~~ * ~~securing items for transport~~ ,haines 2,28,Order new Lifeline buoy batteries,system integration,critical,closed,Buoy-System-2010,task,haines,must have,1291816950,1298578002,Address battery capacity issues before deployment. We either need to order new buoy system batteries or refurbish the older ones. {{{ As of 2/24/2011 }}} Decision has been made to order new batteries (same make and model: Lifeline AGM) and have YSI install them ASAP while the buoys are still at the shop in Marion_ MA. So changing this to system integration component. Order placed with CE BECKMAN CO in Bedford_ MA. {{{ CE BECKMAN CO 11-35 Commercial Street New Bedford MA_ 02740 Marine Wholesale & Service Station Phone: 508-994-9674 Fax: 508-990-2785 http://www.cebeckman.com/ }}} They will deliver batteries to YSI in Marion_ MA tomorrow 2/25/2011.,haines 2,38,Complete Buoy Structure Modifications,hardware,critical,closed,Buoy-System-2010,task,haines,must have,1301509997,1312292734, * contact Jimmy Bircher a local welder to help modify buoy CG * let Jim Bircher and John Wallinga decide best cost-effective solution Bircher_ Inc to do the following work * order s/s rods (~500 lbs) for each buoy * cut and install 4 rods on each buoy * machine bale key-hole bushing using 4140 steal on one buoy {{{ Jimmy Bircher Bircher Inc Machine Shop 119 Industrial Dr. Moreahead City_ NC 28557 bircher@bizec.rr.com 252-726-5470 252-241-5811 (cell) bircherinc.com }}},haines 2,39,Resolve Issues with YSI System Integration,system integration,critical,closed,Buoy-System-2010,task,haines,must have,1301516392,1326301898, * review the upgrades/retrofits to the buoys and tower package * see how the systems are constructed and operating_ and make any changes that might be wise * work through the communications protocols implemented * collect documents and software,haines 2,44,Order Replacement Beacon,hardware,critical,closed,Buoy-System-2010,task,haines,must have,1310483432,1310502119,One of the navigational beacons was full of water. Freddy removed from buoy. Water inside. We have to replace this before deployment. Use same flash pattern listed on Nav Chart for LSRB. Private Aid flash pattern of "Fl Y 4s" (Short flash every 4 seconds) {{{ Carmanah 700 Series Amber Solar powered meets all requirements of USCG in 33 CFR_ part 66 www.carmanah.com 250-380-0052 }}} {{{ Savannah Location: First Choice Marine Supply 122 Pipemaker's Circle Unit 200 Pooler_ GA 31322 Tel: 912-998-0023 Fax: 912-998-0028 savannah@FirstChoiceMarineSupply.com }}},haines 2,60,B1 stopped communicating,communication,critical,closed,Buoy-System-2010,task,haines,must have,1326302463,1330616729,Dec 18_ 2011 at 1300 UTC * No GlobalStar comms with B1 since Dec 18_ 2011 at 1300 UTC * comm Logs on LoggerNet indicate some trouble communicating (extra of extra connects and disconnects within an hour) while several days to weeks prior each connection would get all the data and be done with mostly one call. * GlobalStar VPN is functioning (can ping the loopback and can ping tower package GS modem when on and sat coverage) * monitor for weather window to go visit B1 Jan 11_ 2012 * I've tried direct dial to Iridium Modem on B1 (modem to modem) from Murray Roof but B1 does not answer. Either problem with Iridium -- or not on or larger systemic power issue. This may be more than a comm problem and may change ticket to system if Feb 27_ 2012 * Confirmed B1 destroyed in same manner as B1. See [http://sarahaines.smugmug.com/Work/B1-Destroyed-Feb-27-2012/ photos taken on Feb 27],haines 2,61,B2 stopped communicating,communication,critical,closed,Buoy-System-2010,task,haines,must have,1326303414,1330616642,Dec 29_ 2011 at 1400 UTC * B2 stopped communicating on Dec 29_ 2011 at 1400 UTC * Not sure why GS stopped communicating -- comm logs do not show any awkward behaviour prior * All B2 system data (battery ~12 volts okay_ no leak detection) Jan 06_ 2011 at 1730 * Setup 3rd Iridium on Murray roof and dialed direct to B2 * Initially got in and downloaded table defs_ and got ports and flags * put it in manual mode (flag(2)) but accidentally turned off the iridium power while still in manual mode * This now makes B2 non-functional (no data collection) and I cannot communicate via Iridium since it is off. * Elevating it to critical * monitor for weather window and visit B2 Feb 06_ 2012 * confirmed B2 is destroyed see photos [http://sarahaines.smugmug.com/Work/Buoy-Destroyed-Feb-06-2012/ Photos taken on Feb 06] ,haines 2,3,Draft Tower Safety Plan with Navy,deployment,critical,closed,Tower-System-2010,task,haines,must have,1277837465,1297719727, * Fill out and submit draft Harzards Management Plan (HMP) to UNC EHS. * Work with Navy to complete HMP. ,haines 2,12,Determine if any power and communication requirements for Navy components,deployment,critical,closed,Tower-System-2010,task,haines,must have,1285876473,1297720498,Evaluate the additional bandwidth and power required to support the Navy NRG wind anemometers_ the LIDAR NRG Wind Cube_ Satellite (IMARSAT and GlobalStar) Communications_ in addition to UNC met suite and Scintec SODAR. ,haines 2,33,Finalize Hazards Management Plan (HMP) at UNC,deployment,critical,assigned,Tower-System-2010,task,haines *,must have,1297719449,1297719565, * Fill out and submit draft HMP to UNC EHS. * Work with Navy to complete HMP. * Add to HMP type and range of vessel used for installation and decommission of equipment versus maintenance and operation. ,haines 3,7,Recalibrate RM Young Wind Monitors (1st batch),sensor,major,closed,Buoy-System-2010,task,haines,must have,1277842797,1285952772, * ~~fill out RMA form and send with shipment~~ * ~~ship to RM Young~~ Fedex Ground 9/10/2010 * ~~received quote for repair and cal~~ * ~~returned payment info~~ * 3-4 weeks turn around from email Ryan Phillips at rphillips at youngusa.com,haines 3,8,Recalibrate Eppley PIR and PSP sensors (1st set),sensor,major,closed,Buoy-System-2010,task,haines,must have,1277846514,1289499579, * Get PIR and PSP from Kenan Roof * Contact Eppley Labs about recalibration of 2 sets of PSP and PIR sensors and what arrangements need to be made * Ship and make payment Only need to send contact info with shipment. We will be contacted about costs when received by Eppley. THE EPPLEY LABORATORY_ INC. 12 Sheffield Avenue_ PO Box 419 Newport_ Rhode Island 02840 USA Tel: 401-847-1020 Fax: 401-847-1031 Email: info@eppleylab.com ,haines 3,9,Recalibrate Rotonic Temp/Humidity sensors,sensor,major,closed,Buoy-System-2010,task,haines,must have,1277846580,1289508917, * Obtain RNA from Rotronic * Rotronic web page for services [http://www.rotronic-usa.com/service/calibration%20and%20repair%20service.htm] * shipped to Rotronic,haines 3,10,Reserve ship for buoy deployments,deployment,major,closed,Buoy-System-2010,task,seim,must have,1282853940,1312461343, * Define requirements for ship capability * Determine ship availability * Schedule ship (forms_ port-of-call_ dates) We need about an 80 foot vessel with A-frame or J-frame capable of handling buoy size and weight (13 feet tall non-instrumented_ 15+ feet tall instrumented_ 6.5 fee diameter_ 2200 lbs) and anchor weight (~2800-3000 lbs) plus 30m 3/4" chain and cable. Harvey made contact with several different ships that could help. * R/V Savannah (SKIO) $10K+ per day (too expensive and very busy) * R/V Dan Moore (Cape Fear Community College) $9K+ per day (too expensive) * Some vessels in Virginia (Udel_ Chesapeake Bay buoy tender) * New NOAA SRVx (Monitor National Marine Sanctuary support vessel) The NOAA SRVx vessel and crew are available and capable to handle our deployment requirements. First available time is Aug 18-22. Our alternate deployment window will be early October. Here are some other characteristics and links: {{{ BUILDER:.......................Guardian Marine; Edmonds_ Wash. DESIGN:........................Fiberglass sandwich core construction LENGTH:........................85 feet BEAM:..........................23 feet RANGE:.........................1_700 nautical miles SPEED:.........................35 knots HORSEPOWER:....................Two 2_735-horsepower MTU World PROPULSION: ...................2 MTU 12V 4000 series ACCOMMODATIONS:................3 crew; 4 crew for 24-hour operation A-FRAME:.......................4000 lb limit }}} Here is a link to pictures of the NOAA SRVx * http://oceanexplorer.noaa.gov/explorations/10sbnms/media/slideshow/flash_slideshow.html Contact Info for NOAA SRVx has been through {{{ David W. Alberg Sanctuary Superintendent Monitor National Marine Sanctuary National Oceanic and Atmospheric Administration 100 Museum Drive Newport News_ VA 23606 Phone: (757) 591-7326 Mobile: (757) 869-4291 Fax: (757) 591-7353 www.monitor.noaa.gov }}},haines 3,11,Obtain approval for mooring locations,deployment,major,closed,Buoy-System-2010,task,haines,must have,1282854507,1319811541, * Contact Coast Guard for requirements of registering location and buoy as a Private Aid to Navigation (PATON) * fill out form CG-2554 (blank form attached) * Contact US Army Corp of Engineers to obtain permit or permission to deploy buoys in proposed locations * lighting_ notices_ or placard requirements * charted locations * notice to mariners issued {{{ Thomas W. Flynn LCDR_ USCG (Retired) Marine Information Specialist Tel: (757) 398-6229 FAX: (757) 398-6303 }}} {{{ > Josh R. Pelletier > Regulatory Specialist > United States Army Corps of Engineers > Washington Regulatory Field Office > Post Office Box 1000 > Washington_ North Carolina 27889 > (910) 251-4605 }}} {{{ Dave Timpy at 910-251-4634 US Army Corp of Engineers }}} ,haines 3,14,Recalibrate Seabird CTDs (1st batch),sensor,major,closed,Buoy-System-2010,task,haines,must have,1285950909,1289508978,Ship and have recalibrate first 4 CTDs at Seabird (2 IMPs and 2 SMPs) * Get info on procedure for shipment and return * Instructions: http://www.seabird.com/customer_support/Servreq.htm * After cal_ ship to MA ??,haines 3,15,Recalibrate Seabird CTDs (2nd batch),sensor,major,closed,Buoy-System-2010,task,haines,must have,1285952522,1287505115,Ship and recalibrate CTDs (2 IMPs) * Ship from MA * Delivery to ?? Two new 37-IMPs were sent with buoy system. This ticket is not necessary for this buoy deployment_ hence marking "invalid" since no other option in trac to remove or label it.,haines 3,16,Recalibrate RM Young Wind Monitors (2nd batch),sensor,major,closed,Buoy-System-2010,task,haines,must have,1285952870,1289509006, * fill out RMA form and send with shipment * ship to RM Young * receive quote for repair and cal * returned payment info acceptance * 3-4 weeks turn around from email Ryan Phillips at rphillips at youngusa.com,haines 3,17,Purchase HRM3300 Compass and Tilt Sensor,system integration,major,closed,Buoy-System-2010,task,haines,must have,1285953717,1292452929,After consultation with YSI buoy group_ we will use Honeywell HRM3300. Type they use and it will perform same functions as PNI TCM2 (buoy heading for wind and fast rate 3Hz buoy motion status). * we will need to purchase 2 of these (for now YSI has some in stock they can use) The need to purchase two new buoy compasses was determined on Sept 14_ 2010 while getting the buoys ready to ship to MA. The housing for Buoy 2 was flooded with water up to the brim. Assuming the same on Buoy 1. ,haines 3,22,Order ADCP Batteries,deployment,major,closed,Buoy-System-2010,task,haines,must have,1287004821,1312292662,,haines 3,23,Order Acoustic Release Batteries,deployment,major,closed,Buoy-System-2010,task,haines,must have,1287004843,1298559721,ORE Offshore 4 Little Brook Road West Wareham_ MA 02576 T: 508-291-0960 F: 508-291-0975 Contact our team directly: Greg MacEachern Communication & Control maceachern@ore.com Spoke with Greg MacEachern: Placed order on Feb 16_ 2011 * qty 4 $145 each battery for C.A.R.T P/N B32174-002 * qty 4 $40 each anode sacrafice P/N A977110 The purge manifold is not something they sell. We can construct one with two valves_ nitrogen canister or supply_ and vacuum pump with gauge. ,haines 3,24,Recalibrate Eppley PIR and PSP sensors (2nd set),sensor,major,closed,Buoy-System-2010,task,haines,must have,1287504866,1291933446, * After 1st set calibrated and returned * Package 2nd set for shipment * Ship and make payment Only need to send contact info with shipment. We will be contacted about costs when received by Eppley. THE EPPLEY LABORATORY_ INC. 12 Sheffield Avenue_ PO Box 419 Newport_ Rhode Island 02840 USA Tel: 401-847-1020 Fax: 401-847-1031 Email: info@eppleylab.com ,haines 3,25,Purchase Garmin GPS 16/17 OEM,system integration,major,closed,Buoy-System-2010,task,haines,must have,1289509830,1291668809,YSI determined that one of the GPS units in not working so need a replacement.,haines 3,26,Purchase Xantrex LinkPRO,system integration,major,closed,Buoy-System-2010,task,haines,must have,1291668927,1291668946,Purchase newer model linkPro for buoy and tower systems. Uses less power and has a nice lcd display instead of backlight. ,haines 3,27,Obtain mooring design specifications,hardware,major,closed,Buoy-System-2010,task,haines,must have,1291669929,1301507547,We now have mooring design from John Wallinga. See attachments. [http://trac.nccoos.org/platforms/ticket/27/UNC_30meters.xlsx UNC_30meters.xlsx] ---- * ~~contact John Wallinga at UMaine to go over mooring design steps for buoys.~~ * ~~contact Tony to get inventory of what mooring hardware we have at IMS~~ * ~~contract with John Wallinga at UMaine to design mooring components_ lengths and specifications.~~ John will provide us with a list of parts_ how much or how many_ and suppliers for all the bits and pieces. 1. we need to provide John Wallinga with tidal range_ estimated currents and length of deployment. 2. JW will provide us with a mooring specification and list parts and lengths for these deployments. 3. JW will communicate design specifications of buoy modifications to be done with shop in MHC.,haines 3,30,Activate Globalstar Service,system integration,major,closed,Buoy-System-2010,task,haines,must have,1292943689,1292943958,Fill out and complete any forms to sign up for Globalstar Satellite Service,haines 3,31,Activate INMARSAT Service,system integration,major,closed,Buoy-System-2010,task,haines,must have,1292943925,1299106343,Geoff Morrison with Sea Keepers activated 3 Sat-C transcievers (INMARSAT-C) through Vizada Case #00264366 : request for SatC activation Data will be coded per Sea Keepers protocol to hexadecimal message on each buoy_ the data will be transmitted to private mailbox via satellite comms_ then sea keepers server pulls and decodes message for posting onto Sea Keepers website and posting to FTP site for NDBC and GTS to grab. Examples of how the data will look can be seen on http://data.seakeepers.org ,haines 3,34,Order Acoustic Modem Batteries,deployment,major,closed,Buoy-System-2010,task,haines,must have,1299097326,1312300503, * order extra batteries for LinkQuest UVM1000 acoustic modem * order spare spider cable that connects (one at YSI has broken pin),haines 3,35,Order Mooring Chain and Hardware,hardware,major,closed,Buoy-System-2010,task,haines,must have,1299100032,1303139197, * place order with Steve Tabor at Trawl Works {{{ Trawl Works P.O. Box 34230 Walts Way Narragansett_ RI 02882 Tel:(401) 789-3964 sales@trawlworks.com }}},haines 3,36,Order Wire Rope for Mooring,hardware,major,closed,Buoy-System-2010,task,haines,must have,1301508511,1303139247, * Place order with James Cappellini (james@mooringsystems.com) * (2) 20 meter length of 3/8" jacketed 3 x 19 wire rope with termination {{{ Mooring Systems_ Inc. P.O. Box 413 1227 Route 28A (Map) Cataumet_ MA 02534 Phone: 508-564-4770 Email: sales@mooringsystems.com }}},haines 3,37,Order Railroad Car Wheels for Mooring,hardware,major,closed,Buoy-System-2010,task,haines,must have,1301509062,1304362244, * Place order with Frit Car in Bridgeton_ NC {{{ Frit Car_ Inc Bridgeton_ NC Facility P.O. Box 569 Highway 17 North Bridgeton_ NC 28519 http://www.fritcar.com/ Phone:(252) 638-2675 Fax:(252) 638-5125 Del. Carrier: Norfolk Southern 2 Wheels for $500_ price includes removing axle Gary at Frit is looking for someone to deliver them for us. }}} * Alternative -- RR wheels Jerry Solt at Wheelworx.com {{{ jerry@wheelworx.com 614-325-8071 614-834-4783 $145/wheel and arrange our own drop shipment }}} ,haines 3,40,Test GlobalStar Communication via LoggerNet,communication,major,closed,Buoy-System-2010,task,haines,must have,1303139562,1304429734, * Configure LoggerNet on turb.marine.unc.edu to access each system via GlobalStar Network * Buoy 1 * Buoy 2 Issues raised during testing: * modems set for direct dial via ground station for GlobalStar network -- not static IPs * analog phone line required Successfully tested dial-up to Tower system only from analog line (Sara's home phone). Contacted University Telecommunications. Cost for line analog line to be installed is ~$100 initially_ but service is $50/month (with unlimited long distance). Installing analog line is not a reasonable solution as we can only dial one buoy or system at a time and it will be hard to move (requires additional $100 to move to another telephone port). Opening new tickets ([ticket:42 42] and [ticket:43 43])about service setup and hardware necessary to have static IPs for each GlobalStar modem. ,haines 3,42,Place order for GlobalStar static IP/VPN service,communication,major,closed,Buoy-System-2010,task,haines,must have,1304428502,1310483504, * establish account for static IP to GlobalStar modems_ one time fee $2000 for service_ includes GlobalStar VPN router for campus * return GlobalStar modems to ECI for reconfiguring $150 per modem for static IP {{{ David O'Hara NETSAT Office Direct: 303-683-4843 Fax: 866-880-7069 Cell: 303-229-7222 david.ohara@netsat.info www.netsat.info }}} {{{ Ron Mozer attn. Crystalline_ 210 Riverview Dr. Monessen PA. 15062 }}},haines 3,43,Configure and Test GlobalStar VPN and static IPs,communication,major,closed,Buoy-System-2010,task,haines,must have,1304428811,1326813162, * contact ITS to obtain two subnets required for VPN router to Globalstar (GS). * all three modems reconfigured for static IP * once GS VPN router arrives_ contact ITS again for port forwarding allocations so public computer (turb.marine.unc.edu) can access the VPN router * setup and test Globalstar VPN router on campus with GS loopback adapter * install and setup second ethernet adapter for turb.marine for VPN connection * change registry setting on turb.marine to allow additional polling per instructions from Ron Mozer at Crystalline * test GS modems with ping and test telnet The phone numbers of our GlobalStar/ExtraNetCC satellite units: {{{ ESN: 11601178763 / Phone# 999-008-1921 / IP: 10.1.64.1 (Buoy) ESN: 11601178914 / Phone# 999-008-1922 / IP: 10.1.64.2 (Buoy) ESN: 11601178933 / Phone# 999-008-1923 / IP: 10.1.64.3 (Tower) }}} {{{ Adair Thaxton Network Specialist_ ITS Networking 440 W. Franklin St._ Suite 1011 UNC Chapel Hill_ (919) 445-9387 sthaxton@email.unc.edu }}} {{{ Matt Lord Manager_ Communications Engineering Globalstar 461 S. Milpitas Blvd. Milpitas_ CA 95035 P. 408.933.4507 matt.lord@globalstar.com }}} {{{ Brian Nordman | Crystalline Technology ??? | Monessen | PA | 15062 | USA T 724-638-8048 | M 724.557.8474 Brian@Crystalline.us Ron Mozer | Crystalline Technology ??? | Monessen| PA | 15062 | USA T 724-638-8048 | ron@Crystalline.us }}} This ticket is follow-on to ticket titled "Testing Globalstar from Loggernet" (ticket:40) where testing was successfully completed on straight dialup and "Setup GlobalStar static IP/VPN service" (ticket:42) where the order was placed for VPN IP service through NetSat and David O'hara. ,haines 3,45,Place order for Iridium/Rudics static IP service,communication,major,closed,Buoy-System-2010,task,haines,must have,1310483693,1335966497,order for Iridium/Rudics static IP service * contact Joubeh to begin order for Rudics * provide static IP of server a_ port number and a group name * or Mobile Terminated (telnet) just an IP * activate modems with email to Joubeh once Iridium as confirmed connection and group name Intructions from Joubeh: "Once we have confirmation from Iridium that the connection is completed we will be in touch and provide the RUDICS group name and account number for activation purposes." ,haines 3,46,Configure and Test Iridium/Rudics static IPs,communication,major,closed,Buoy-System-2010,task,haines,must have,1310483779,1335962305, * Establish Rudics service through Joubeh_ * request activation of SIM's through Joubeh (see attached instructions) * tested Iridium modems using CSI Loggernet. There are telnet handshaking commands to issue to the ground station that they call the specifically assigned MSISDN-C number. ,haines 3,47,Re-assemble anchors,hardware,major,closed,Buoy-System-2010,task,haines,must have,1312299480,1312299490, * re-assemble stacks of three (3) RR car wheels on original spindles * tack weld together to secure for loading and deployment ,haines 3,48,Assemble and check mooring hardware,hardware,major,closed,Buoy-System-2010,task,seim,must have,1312299935,1312299968, * layout and verify all parts for mooring hardware * determine all mechanical connections and links * determine size of swivels for sizing sacrificial anodes * purchase axle-shaft anodes for swivels * determine diameter of cabling to determine SBE Inductive Modem CTDs and Inductive Coupling Cables (ICC) have proper delrin fittings. NOTE: at West Marine_ in Morehead City_ can use IMS account for discount on many items,haines 3,49,Order from SBE additional Inductive Cable Coupler (ICC),sensor,major,closed,Buoy-System-2010,task,seim,must have,1312300113,1312300118, * order second Inductive Cable Coupler (ICC) for B2 from SeaBird Electronics (SBE),haines 3,50,Test BrightWaters,deployment,major,closed,Buoy-System-2010,task,haines,must have,1312461139,1318365626,Brightwaters Argos/GPS Mooring Monitors PTT #22363 and #22438 * Both BrightWaters Argos trackers need to tested * test battery capacity (before charge_ after charge and hold charge) * test tracking thru Argos Satellite * confirm GPS posn tracking thru messaging Tests and prep completed: * PTT 22438 battery replaced 24.5v (old one was dead -- 1.5v) * PTT 22363 battery okay 23.9v * Argos position show up on argosweb -- https://argos-system.clsamerica.com/cwi/Consult.do for Chapel Hill * And again after "superreset" at IMS * Decoded message of GPS data sent by Mooring Monitor over Argos_ using ARG104.exe. ,haines 3,51,Configure ADCPs,sensor,major,closed,Buoy-System-2010,task,haines,must have,1312461212,1318366853, * configure ADCPs * test configuration * install fresh batteries Name deployment Wind 2011 B1 or B2 to replace default filename on ADCP. RNW11B1 or RNW11B2 Configuration Work Plan settings as follows {{{ CR1 CF11101 EA0 EB0 ED300 ES35 EX11111 EZ1111101 WA255 WB0 WD111100000 WF88 WN35 WP50 WS100 WV175 HD111000000 HB5 HP2400 HR06:00:00.00 HT00:00:00.50 TE00:30:00.00 TP00:36.00 CK CS ; ;Instrument = Workhorse Sentinel ;Frequency = 614400 ;Water Profile = YES ;Bottom Track = NO ;High Res. Modes = NO ;High Rate Pinging = NO ;Shallow Bottom Mode= NO ;Wave Gauge = YES ;Lowered ADCP = NO ;Ice Track = NO ;Surface Track = NO ;Beam angle = 20 ;Temperature = 10.00 ;Deployment hours = 4320.00 ;Battery packs = 1 ;Automatic TP = YES ;Memory size [MB] = 448 ;Saved Screen = 2 ; ;Consequences generated by PlanADCP version 2.06: ;First cell range = 2.10 m ;Last cell range = 36.10 m ;Max range = 43.93 m ;Standard deviation = 0.99 cm/s ;Ensemble size = 854 bytes ;Storage required = 135.63 MB (142220160 bytes) ;Power usage = 489.44 Wh ;Battery usage = 1.1 ;Samples / Wv Burst = 2400 ;Min NonDir Wave Per= 2.59 s ;Min Dir Wave Period= 4.31 s ;Bytes / Wave Burst = 187280 ; ; WARNINGS AND CAUTIONS: ; There are not enough battery packs for the deployment. (1 battery pack(s) will last 165 days). ; Waves Gauge feature has to be installed in Workhorse to use selected option. ; Advanced settings have been changed. }}},haines 3,52,Configure CTDs,sensor,major,closed,Buoy-System-2010,task,haines,must have,1312461246,1318366218, * Configure CTDs for deployment * install fresh batteries On deck issued "stop" and to stop waiting for start time_ then issued "startnow" to manual force sampling to start. {{{ S>ds SBE37-SM V 2.5 SERIAL NO. 3584 05 Oct 2011 22:06:35 not logging: waiting to start at 06 Oct 2011 12:00:00 sample interval = 360 seconds samplenumber = 0_ free = 190650 transmit real-time data do not output salinity with each sample do not output sound velocity with each sample store time with each sample number of samples to average = 4 serial sync mode disabled wait time after serial sync sampling = 30 seconds temperature = 23.16 deg C S>stop S>startnow start now }}} Confirmed pumping within about 6 minutes.,haines 3,53,Configure and Test Pop-up Releases,deployment,major,closed,Buoy-System-2010,task,haines,must have,1312461486,1318367113, * test ORE acoustic releases and install new batteries * test with deck unit * purchase new rope for both pop-ups Prepared and tested 29207 and 31224. 29207 is so corroded shaft arm no working so sending it to ORE Offshore (RMA 2033) to get fixed. Used 30608 -- already new battery but checked oil leak on transducer head and replaced screw where small leak was dripping. There was not much mineral oil lost and tested unit works fine.,haines 3,54,Prepare Bottom Frames,deployment,major,closed,Buoy-System-2010,task,haines,must have,1312461676,1318366894, * tape sensors for antifoulant * mount ADCP_ CTD * install pop-up canistor and rope * mount acoustic release * mount sacrificial anodes ,haines 3,55,Order SBE 37 CTD batteries,sensor,major,closed,Buoy-System-2010,task,haines,must have,1318531540,1319209755,Seabird does not make older batteries p/n 50243.1 (80981.1 ??) with 6 batteries. We need to buy the retrofit battery holder for all our units younger than 1999. Our oldest CTD is 2001 so the retrofit (red) lithium battery holder will work in all of our units. The retrofit holders (p/n 801797) are $150/each. Lithium battery packs (12 AA batteries) (p/n 50441) cost $90/each. We get a 15% educational discount. Ordered 7 holders and 14 battery packs.,haines 3,56,Repair Acoustic Release s/n 29207,deployment,major,closed,Buoy-System-2010,task,haines,must have,1318532274,1326300701,While testing acoustic releases (ticket:53) for deployment on bottom frames found s/n 29207 to be corroded such that the shaft arm to rotating even though unit response to command codes. Sent it to ORE Offshore (RMA 2033) to get fixed. ,haines 3,57,Order Marine Model Antenna for GlobalStar Modems,communication,major,closed,Buoy-System-2010,task,haines,must have,1318532897,1319810949,Problem: GlobalStar modem on B2 only connects during calmer seas. Patch antenna that was spec'd for us is best for land applications. There is a marine model "stick" that should be better for the rougher seas and buoy application. However it requires a adaptation since the antenna is taller than the low-profile puck originally installed. * order 2 marine models If the marine-model antenna does not fit inside canister: * drill holes on canister lid for antenna cable pass-throughs * mount antenna on poll or on plastic shelf with radiometers * make a longer canister and mount inside I doubt we want to mount the antenna on top of the GlobalStar canister as it will compromise how sealed to elements it is. We have opted for the third option. See ticket:58. ,haines 3,58,Make larger canister for GlobalStar modem and new_ longer antenna,communication,major,closed,Buoy-System-2010,task,haines,must have,1319208626,1319810731,As suspected (ticket:57)_ the canister that holds the Globalstar modems is too short for the new_ longer Quarafilar Helix (QFH) antenna. The patch antenna is 1.5" long. The new QFH antenna is 7" long. Drilling holes in existing canister and mounting the antenna on end-cap may compromise the waterproofing of the pod. Instead_ we need to have Physics Shop at UNC make a longer canister so we can field swap the antenna on mount inside the canister_ and swap canisters. * get specs from YSI for lathing grooves and drilling holes for trimmer-string in * purchase 5 feet of Sch80 5" PVC Pipe and Type I 0.5" thick (12"x24") PVC Sheet * get materials and specs to Physics shop ,haines 3,59,Order crimping tools and supplies for re-wiring to terminals in the integrated systems,system integration,major,closed,Buoy-System-2010,task,haines,must have,1319209886,1319209985,YSI system as built is designed for quick swapping of instruments_ but requires crimping ferrule connector to wires for better physical and electrical contact within the terminal blocks. ,haines 3,63,Remove B1 and B2 ARGOS PTTs from service,communication,major,closed,Buoy-System-2010,task,haines,must have,1330705954,1330705963,Contact CLS America user services to have ARGOS PTT ids 22363 and 22438 removed from our id list. ,haines 3,64,Remove B1 and B2 GlobalStar numbers from service,communication,major,closed,Buoy-System-2010,task,haines,must have,1332190781,1335966401,David O'hara is looking into removing the two modems from service. {{{ 11601178763/ 999-008-1921 11601178914/ 999-008-1922 }}} {{{ David O'Hara NETSAT Office Direct: 303-683-4843 Fax: 866-880-7069 Cell: 303-229-7222 david.ohara@netsat.info www.netsat.info }}},haines 3,65,Resolve comm problem between CSI Loggernet and Iridium RUDICS,communication,major,assigned,Buoy-System-2010,task,haines *,must have,1335962885,1335962893, * Connect to CSI DataLogger CR1000 via Rudics/Iridium and CSI LoggerNet using telnet session with static IP_ CR1000 responds and accepts the connection but never gets table definitions. * Contacted DJ Snodgrass at CSI-Canada. He worked on it some but had to stop. * Spoke with Kevin Simpson at YSI -- They have some upcoming project(s?) that need to resolve this issue too. YSI might be working on it too.,haines 3,4,Get info on ASIMET purchase and recalibration,sensor,major,closed,Tower-System-2010,task,haines,must have,1277837612,1277839374, * Contact Geoff Allusp at WHOI for cost estimate on recalibrating ASIMET HRH_ BARO_ PSP_ PIR_ and RAIN modules. * contacted Jason Smith at WHOI * Contact Victor Neagoe at Star Engineering for cost estimate for four (4) wind modules. * also need lead times for this work,haines 3,5,Order New WIND ASIMET Modules,sensor,major,closed,Tower-System-2010,task,haines,must have,1277838869,1284515490,Purchase four (4) * get quote from Star on company letter head (specify 50% upfront/ 50% 30days after delivery) * write soul source justification for using Star * submit to Paige to get have Purhasing issue a PO and cut check for 50% * 2 weeks in purchasing * 8-10 weeks lead time to build,haines 3,6,Recalibrate ASIMET modules,sensor,major,closed,Tower-System-2010,task,haines,must have,1277838990,1288270578, * ~~Contact Jason Smith at WHOI for instructions~~ (jsmith at whoi dot edu). * ~~Order reusable crate for shipping~~ * ~~Order packing material~~ * ~~Ship ASIMET suite to WHOI~~ * Jason will assess for any repairs and return a quote of cost to repair and calibrate. * get PO or check cut for cost (may need justification letter),haines 3,13,Obtain vessel information,deployment,major,closed,Tower-System-2010,task,haines,must have,1285876825,1285951447, * Reed Meredith_ Wahoo (Wanachese_ NC) 43 foot http://sarahaines.smugmug.com/Work/Wahoo-Wanachese-NC-Sept-25/ * Capt. Krage Gardiner_ Fin Galley_ (Oregon Inlet_ NC) 50 foot http://sarahaines.smugmug.com/Work/Fin-Galley-Oregon-Inlet-Sept/,haines 3,18,Determine power and communication requirements for UNC components,system integration,major,assigned,Tower-System-2010,task,haines *,must have,1286407302,1297720210,Evaluate the power consumption of each sensor and data amounts that would be downloaded every hour for SODAR_ ASIMET Suite_ and Bottom ADCP and CTD (using an acoustic modem_ if there is an existing pull-tube).,haines 3,19,Determine vessel availability and cost,deployment,major,closed,Tower-System-2010,task,haines,must have,1286407667,1286407691,Determine cost and availability of commercial fishing vessels to transit to and from towers and support operation. ,haines 3,20,Determine feasibility for camera system,deployment,major,closed,Tower-System-2010,task,haines,desired,1287004731,1297720124, * Contact Kurt Myers at ILN to see if a camera can be incorporated into any of the Wind systems or what it would take to accomplish this function * Type of camera_ storage_ comm to computer_ delivery of images * Determine comm bandwidth to get images back once a day or hour,haines 3,21,Determine if pull-tube can be installed,deployment,major,assigned,Tower-System-2010,task,haines *,desired,1287004791,1297720150, * Contact Dave Malone to see if he can install if we provide the tube,haines 3,29,Determine capacity and condition of sealed Pb-Acid batteries,deployment,major,closed,Tower-System-2010,task,haines,must have,1291817838,1367521035,Determine if batteries slated for deployment can charge and hold intended capacity.,haines 3,32,ship tower box to YSI,system integration,major,closed,Tower-System-2010,task,haines,must have,1294439397,1297710119,package and ship tower box to YSI ,haines 3,41,Test GlobalStar Communication via LoggerNet,communication,major,closed,Tower-System-2010,task,haines,must have,1303139728,1326301075, * Configure LoggerNet on compass.marine.unc.edu to communicate via GlobalStar to the DataLogger Tower System * Ping 10.1.64.3 -- test okay * Table Defs downloaded -- test (started but not completed) * Data Download Experiencing the same problems as with buoys -- not much time with satellite overpass plus limited sky view on Murray Hall roof access.,haines 4,62,Repair Wind Dir on ASIMET s/n UNC235,communication,minor,assigned,Tower-System-2010,task,haines *,must have,1326461276,1326461284,After installing all the ASIMET modules on the roof of Murray_ and some run time_ determined that one of the ASIMET wind modules is not returning Wind direction * confirm that only wind vain and maybe tilt y and x_ and heading). * get RMA from WHOI * return to WHOI for repair,haines