Ticket Summary Owner Type Priority Component Version
7Recalibrate RM Young Wind Monitors (1st batch)hainestaskmajorsensor
8Recalibrate Eppley PIR and PSP sensors (1st set)hainestaskmajorsensor
9Recalibrate Rotonic Temp/Humidity sensorshainestaskmajorsensor
10Reserve ship for buoy deploymentsseimtaskmajordeployment
11Obtain approval for mooring locationshainestaskmajordeployment
14Recalibrate Seabird CTDs (1st batch)hainestaskmajorsensor
15Recalibrate Seabird CTDs (2nd batch)hainestaskmajorsensor
16Recalibrate RM Young Wind Monitors (2nd batch)hainestaskmajorsensor
17Purchase HRM3300 Compass and Tilt Sensorhainestaskmajorsystem integration
22Order ADCP Batterieshainestaskmajordeployment
23Order Acoustic Release Batterieshainestaskmajordeployment
24Recalibrate Eppley PIR and PSP sensors (2nd set)hainestaskmajorsensor
25Purchase Garmin GPS 16/17 OEMhainestaskmajorsystem integration
26Purchase Xantrex LinkPROhainestaskmajorsystem integration
27Obtain mooring design specificationshainestaskmajorhardware
30Activate Globalstar Servicehainestaskmajorsystem integration
31Activate INMARSAT Servicehainestaskmajorsystem integration
34Order Acoustic Modem Batterieshainestaskmajordeployment
35Order Mooring Chain and Hardwarehainestaskmajorhardware
36Order Wire Rope for Mooringhainestaskmajorhardware
37Order Railroad Car Wheels for Mooringhainestaskmajorhardware
40Test GlobalStar Communication via LoggerNethainestaskmajorcommunication
42Place order for GlobalStar static IP/VPN servicehainestaskmajorcommunication
43Configure and Test GlobalStar VPN and static IPshainestaskmajorcommunication
45Place order for Iridium/Rudics static IP servicehainestaskmajorcommunication
46Configure and Test Iridium/Rudics static IPshainestaskmajorcommunication
47Re-assemble anchorshainestaskmajorhardware
48Assemble and check mooring hardwareseimtaskmajorhardware
49Order from SBE additional Inductive Cable Coupler (ICC)seimtaskmajorsensor
50Test BrightWatershainestaskmajordeployment
51Configure ADCPshainestaskmajorsensor
52Configure CTDshainestaskmajorsensor
53Configure and Test Pop-up Releaseshainestaskmajordeployment
54Prepare Bottom Frameshainestaskmajordeployment
55Order SBE 37 CTD batterieshainestaskmajorsensor
56Repair Acoustic Release s/n 29207hainestaskmajordeployment
57Order Marine Model Antenna for GlobalStar Modemshainestaskmajorcommunication
58Make larger canister for GlobalStar modem and new, longer antennahainestaskmajorcommunication
59Order crimping tools and supplies for re-wiring to terminals in the integrated systemshainestaskmajorsystem integration
63Remove B1 and B2 ARGOS PTTs from servicehainestaskmajorcommunication
64Remove B1 and B2 GlobalStar numbers from servicehainestaskmajorcommunication
1Inventory of Sensorshainestaskcriticalsensor
2Prepare buoys for shipment to YSIhainestaskcriticalsystem integration
28Order new Lifeline buoy batterieshainestaskcriticalsystem integration
38Complete Buoy Structure Modificationshainestaskcriticalhardware
39Resolve Issues with YSI System Integrationhainestaskcriticalsystem integration
44Order Replacement Beaconhainestaskcriticalhardware
60B1 stopped communicatinghainestaskcriticalcommunication
61B2 stopped communicatinghainestaskcriticalcommunication